Foundation ready to pour.....
Foundation poured
1st wall going up with the help of Josh, James, Randy & Chuck
2nd wall going up
3rd wall going up
Josh helping out with the washers & nuts
Abby getting her chance to help with the washers and nuts, too
July 5 - at the end of the day - all of the downstairs, outside wall are up - except the front of the garage. Another day...
Now, You are caught up!
We have a contract on our house and they are coming to do an inspection on Wednesday. Pray that they find very little that will need to be addressed. We will only have until July 16 to "fix" anything that needs "fixin". They want to close by August 6. We do have a place to rent that is close to work (for Sheree) and close to this new place we are building. Please pray for us as we go through these next few weeks with all that will be going on for us. All of this, plus our trip to Australia to visit Matt & Tiff and of course new little "Roo"!!!! Then our mission trip to Montana after we return from Australia. Busy, Busy, Busy summer. Keep watching for more updates - will try to do better! :)